PROJ-003
Dashboard Overview
Site Engineer Mode
PO Value
📄
₱150,000.00
Contract baseline value
Proposed Budget
👛
₱112,700.00
Target Cost Limit
Actual Spent
💳
₱92,300.00
81.9% Executed
Remaining Balance
🏦
₱20,400.00
Margin: ₱37,300.00 (24.9%)
Line-Item Cost Variance (BOQ vs Proposed vs Actual)
High Margin Items Summary
| Line Item Description | PO Total | Proposed Target | Est. Margin |
|---|---|---|---|
| Starlink Gen3 Satellite Kit | ₱35,000.00 | ₱28,000.00 | ₱7,000.00 |
| Ruijie Reyee Indoor & Outdoor APs | ₱18,000.00 | ₱14,000.00 | ₱4,000.00 |
| Engineering Labor & Field Survey | ₱20,000.00 | ₱10,000.00 | ₱10,000.00 |
Project Health
Budget Utilization
81.9%
Pending PR Requests
1 Pending
Total Recorded ORs
3 Receipts Recorded
Recent Requisitions
PR-801 • Starlink Dish Set
Starlink Philippines
₱28,000.00
APPROVED
PR-802 • Ruijie Access Points
Ruijie Direct
₱14,000.00
APPROVED
PR-803 • Site Survey & Labor
NetTech Solutions
₱10,000.00
PENDING
BOQ Breakdown vs Proposed Line-Item Budget
| Line Item Description | Qty / Unit | PO Unit Price | PO Total | Proposed Unit Budget | Proposed Total Target | Est. Profit Margin |
|---|---|---|---|---|---|---|
| Starlink Gen3 Satellite Kit | 1 Set | ₱35,000.00 | ₱35,000.00 | ₱28,000.00 | ₱28,000.00 | ₱7,000.00 (20%) |
| Ruijie Reyee Indoor/Outdoor APs | 2 Units | ₱9,000.00 | ₱18,000.00 | ₱7,000.00 | ₱14,000.00 | ₱4,000.00 (22.2%) |
| CommScope Cat6 Cable Roll | 2 Rolls | ₱8,500.00 | ₱17,000.00 | ₱6,000.00 | ₱12,000.00 | ₱5,000.00 (29.4%) |
| Heavy Duty Cable Conduit & Mouldings | 1 Lot | ₱10,000.00 | ₱10,000.00 | ₱5,000.00 | ₱5,000.00 | ₱5,000.00 (50%) |
| Engineering Installation & Survey Labor | 1 Lot | ₱20,000.00 | ₱20,000.00 | ₱10,000.00 | ₱10,000.00 | ₱10,000.00 (50%) |
Purchase Requests & Requisitions
| PR # | Requested Item | Category | Requested Amount | Status | Action |
|---|---|---|---|---|---|
| PR-801 | Starlink Gen3 Satellite Kit | Materials | ₱28,000.00 | APPROVED | |
| PR-802 | Ruijie Reyee Indoor & Outdoor APs | Materials | ₱14,000.00 | APPROVED | |
| PR-803 | Site Survey & Installation Labor | Labor | ₱10,000.00 | PENDING |
Actual Expense Ledger & Official Receipts (ORs)
| OR Number | Date Recorded | Description | Vendor | Amount Paid | Official Receipt (OR) |
|---|---|---|---|---|---|
| OR-2026-001 | Sep 12, 2026 | Starlink Gen3 Hardware Purchase | Starlink PH Direct | ₱28,000.00 | |
| OR-2026-002 | Sep 14, 2026 | Ruijie Wi-Fi 6 Access Points | Ruijie Official Store | ₱14,000.00 | |
| OR-2026-003 | Sep 18, 2026 | CommScope Cable & Conduits | BuildPro Hardware | ₱17,000.00 |
Cost vs PO Value Comparison
Category Breakdown